Skip to content
ROENHU

A number · Locuri

The Olt in Steps: 20 Hydropower Plants and a Project Begun in 1989

Seen from above, the Olt looks less like a river than a chain of lakes. The number that explains it is 20. Farther upstream, in the gorge, a staircase of dams begun in 1989 is still unfinished: its last two steps received environmental approval only in September 2026.


Adi Coco·October 30, 2026·3 min·
The Olt in Steps: 20 Hydropower Plants and a Project Begun in 1989
Photo: AdiCoco.com
The Olt River gorge seen from the air between Brezoi and Călimănești, the river wide and still between wooded slopes
The Olt gorge between Brezoi and Călimănești, September 2024.Photo: AdiCoco.com

Between Brezoi and Călimănești, the Olt seems to stand still. From above, the river has the sheen of standing water: wide, gray-green, without a ripple, with the national highway pressed against its bank.

The explanation is a number: 20. That is how many hydropower plants Hidroelectrica owns on the middle and lower Olt, according to a report filed with the stock exchange in May 2025. On a river without waterfalls, the drop a turbine needs is usually created by raising the water behind a dam. Repeat that 20 times and the river changes shape: a step of still water, a dam, another step.

The Gura Lotrului dam and power plant at Brezoi seen from the air, with the reservoir in the foreground, the river downstream, and the railroad and DN7 highway along the banks
A complete step at Brezoi: the Gura Lotrului reservoir in the foreground, the river downstream and, along the banks, the railroad and the DN7 highway, June 2021.Photo: AdiCoco.com

Farther upstream, in the gorge between Avrig and Cornetu, the staircase has gaps. Five steps were planned there in 1989. Thirty-seven years later, two are still far from finished.

Islands of vegetation growing on the Olt, seen from the air, with the DN7 highway and a village on the far bank
Islands of vegetation grow on the still water near Brezoi, June 2021.Photo: AdiCoco.com

River, Road and Rail

Anyone who has driven down the gorge knows how close the water is: the DN7 runs a few yards from it, and in places right above it. The narrow corridor holds the river, the national highway and the railroad linking Transylvania with Oltenia. In stretches, the highway runs on a viaduct, its piers standing in the water. That crowding would end up holding back one of the plants for nearly a quarter-century.

The DN7 highway on a viaduct, following a tight bend of the Olt, seen from above as a bird would see it, with high-voltage lines crossing the water
The DN7 follows a bend of the Olt on a viaduct, August 2022.Photo: AdiCoco.com
The old, rusted railroad bridge at Proieni beside the newer white-painted bridge that trains use today, seen from above over the Olt
The old railroad bridge at Proieni (an 1899 steel structure and a listed historic monument), next to the bridge trains use today, June 2021.Photo: AdiCoco.com

The Missing Steps

At Robești, the construction sign still stands at the plant's entrance, its paint peeling. It lists building permit No. 98, issued May 26, 1989, by the Vâlcea County People's Council, a construction start in 1989 and a completion date of Dec. 20, 2011. Twenty-two years for a single step.

The peeling construction sign of the Robești hydropower plant, with the plant building and a high-voltage pylon behind it under an overcast sky
The sign at the entrance to the Robești plant: a permit dated May 26, 1989, issued by an institution that no longer exists, October 2026.Photo: AdiCoco.com
The Robești dam and its gates, seen from the ground, with the Olt flowing downstream
The Robești dam, in operation since 2012, October 2026.Photo: AdiCoco.com

Robești is one of five steps planned along the roughly 34 miles (55 kilometers) between Avrig and Cornetu. From upstream to downstream, they are Racovița, Lotrioara, Câineni, Robești and Cornetu. Cornetu has been running since 2002, Robești since 2012.

Racovița was inaugurated Dec. 19, 2013, and in July 2026 Romania's Energy Ministry listed it as 95% complete. The plant generates power, but under water-level restrictions: the weir downstream of it cannot be removed until the railroad bridges farther down are protected. At the inauguration, the bridge problem was described as having held up the work for 24 years.

The Robești dam seen from the ground across the Olt Valley railroad, with autumn slopes behind
The Olt Valley railroad and the Robești dam, in the same corridor, October 2026.Photo: AdiCoco.com

The other two steps are even further from completion. In July 2026, Câineni stood at 24% and Lotrioara at 1%; funding for Lotrioara had been cut off in 1992. On Sept. 21, 2026, the Environment Ministry issued the environmental approval for completing the project. Land expropriations and a building permit come next, and the approval can be challenged in court. Estimates cited after it was issued put completion at 2031 for Câineni and 2032 for Lotrioara.

Once finished, the project would have 131 megawatts of installed capacity, according to the Energy Ministry. The Environment Ministry estimates the investment will contribute 156.8 gigawatt-hours a year to national output, the annual consumption of more than 52,000 households.

The crest of the Robești dam, with the reservoir on the left and dam equipment in the background
On the crest of the Robești dam, with the reservoir upstream: the step seen from inside, October 2026.Photo: AdiCoco.com
The Olt widened like a lake north of Râmnicu Vâlcea, with a reed island in the middle of the water, in winter
The Olt north of Râmnicu Vâlcea, widened around a reed island, January 2025.Photo: AdiCoco.com

Toward Râmnicu Vâlcea, the lakes widen until they hold islands of reeds. The Olt still reaches the Danube. It just gets there in steps, and two of them have been waiting since 1989.

The aerial photographs were taken between June 2021 and November 2025, along the stretch between Brezoi and Râmnicu Vâlcea; each caption gives the year. Robești was photographed from the ground on Oct. 26, 2026, when the details on the construction sign were also recorded. Câineni and Lotrioara are not pictured. All other figures come from written sources.


Sources

This English version is an automatic translation of the Romanian original.

Newsletter

If you like what you're reading, subscribe.

New articles in your inbox. At most twice a month. No ads.

AC

Fotoreporter

Adi Coco

Adi Coco este fotograf, fotoreporter, specialist în comunicare și membru FEP (Federation of European Photographers)